The Canadian Ministry of Environment (MOE) approved the wind power project in October 2013 and construction began in October 2014. The project became operational in February 2016 and is expected to meet power requirements of approximately 70,000 Ontario households. The project created more than 350 construction jobs and up to 15 permanent jobs upon commissioning. The onshore wind farm is spread over 46,000 acres mostly located on leased, privately owned lands in Kincardine in Bruce County, Ontario, approximately 3km from Lake Huron. The project's original developer Acciona Renewable Energy Canada Holdings sold it to the SP Armow Wind Ontario joint venture in August 2011.